Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task A 8 B 8.8 C 9.1 D 9.7 E 10.5
QUEST Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration. A 0.5 B 1 C 1.8 D 2.2 E 2.8