下面是这道题目的英文原题,供你参考 During the execution of a project, a large number of changes are made to the project. The project manager should? A. Wait until all changes are known and print out a new schedule B. Make changes as needed but retain the schedule baseline C. Make changes as needed D. Talk to management before any changes are made