回econxing:It is not feasible or necessary to quantify every risk. Therefore, a risk audit should never have as an objective to ensure that each project risk has a computed expected value. [Controlling]Carter et al. 1994, 132 我只能给出你我的答案的理由和出处,你可以查一下,另外说明一下,这些是我们拿到的PMI试题,所有的答案和解释都是标准的。而且,对于答案C,这肯定是风险Audit的目标,以确认风险控制的效果。