The customer increased your project scope by 65%. This increased your cost estimate fivefold. Now you must change the scheduled start and finish dates in your approved project schedule. Your first step should be to— A. Rebaseline the schedule B. Modify the contract C. Use a new target schedule D. Add resources
-------------------------------------------------------------------------------------------------------- To me, the past is black and white, but the future is always colorful. 人生没有彩排,只有现场直播