PMP认证考试试题精选四 61. At what point inthe project is there the most risk of project failure? A. Close out B. Development C. Implementation D. Concept
ANS: D Reference: PMBOK 2.1.2 62. Phase exits, kill points and stage gates are used for what purpose? A. Planning the next stage in the project B. Communicating milestones to stakeholders C. Determining if the project should continue into the next phase D. Measuring earned value
ANS: c Reference: PMBOK 2.1.1 63. A complex project will fit best in what type of organization? A. Functional B. Cross-functional C. Matrix D. Balanced ANS: c Reference: PMBOK 2.3.1 64. Which knowledge area involves organizational theory as a tool/technique? A. Communications Management B. Cost Management C. Risk Management D. Human Resource Management