  从PMP角度看电站EPC运输管理
 

EPC电站海外项目除PMBOK2004提到的9大知识领域内容外,还涉及到物流管理(这是一个比较时髦的叫法,其实我们日常工作都叫运输管理)。电站EPC项目的运输工作涉及到:根据工程进度计划编制发运计划、根据对外合同价格和对内采购合同编制价格拆分表、根据现场进度安排设备材料集港发运、准备运输文件、国内报关、国外清关、国外运输(包括大件)、现场交接等,还会涉及到保险索赔。国外项目,是否能顺利的完成每批货物运输也是项目成功的关键因素之一。所以这些年的项目管理工作经历告诉我,应该重视运输管理。结合目前的工作,在PMP的知识构架下我试图对运输管理进行细分。

 

Logistics (transportation) management

 

  • Project Cargoes Delivery schedule
  • Manage logistics
  • Develop Shipment Documents
  • Monitoring and controlling logistics
  • Correct Document

 

Project Cargoes Delivery schedule

  Input: Project Schedule

                        Project Execution Plan

                        Enterprise Environment Factors

                        Organizational Process Assets

  Tool and technical:

                        Contract Price Schedule

                        Excel

                        Power Station Knowledge

  Output

                        Project cargoes delivery scheduled

 

Manage logistics

  Input: Project cargoes delivery scheduled

                        Approved Corrective action              

  Tool and technical:

                        Management methodology

                        Management information system

  Output

                        Performance report

 

Develop shipping documents

Input:    Project cargoes delivery schedule

                        Contract stipulation

                        Enterprise Environment Factors

                        Organizational Process Assets

  Tool and technical:

                        Knowledge of trade

  Output

                        Record list

                        L/C

                        B/L

                        Packing list (including detail)

                        Original Certificate

                        Quality Certificate

                        Invoice

 

Monitoring and controlling logistics

Input:    Project cargoes delivery schedule

                        Performance report

                       

  Tool and technical:

                        Management methodology

                        Information system

                        Expert Judgment

  Output

                        Recommended Corrective action

                        Feedback

Forecast

                       

Correct Shipment Document

  Input: Project cargoes delivery schedule

                        Performance report

                        Shipping document

                       

  Tool and technical:

                        Information system

                        Expert Judgment

  Output

                        Updated shipping document

 

 

 