To answer a post related to dependency in project management, I checked
Wikipedia to find out what that is and got some additional information
even though the answer googled obviously failed. There are some explaination for DEPENDENCY with short but visualized sentences as following: -------------------------------------------------------------------------------------------------------
There are three kinds of dependencies with respect to the reason for the existence of dependency:
- Causal (logical)
- It is impossible to edit a text before it is written
- It is illogical to pour concrete before you dig the foundations
- Resource constraints
- It is logically possible to paint four walls in a room simultaneously but there is only one painter
- Discretionary (preferential)
- I want to paint the living room before painting the dining room, although I could do it the other way round, too
|